You are here: Home / Case Studies / Refurbishment of 2 steel TLX filters at Lymington Leisure

Refurbishment of 2 steel TLX filters at Lymington Leisure

May 03, 2013 at 12:09 PM

Client: New Forest District Council

Main Contractor: Bluewater Swimming Pools

Project Overview

This project was carried out at Lymington Leisure, our scope of works included the refurbishment of 2 steel TLX filters each one being 2.4m in diameter.

Both filters were removed of the existing filter sand, the under drains, headers and nozzle plates were all removed and replaced with new.

The internal surfaces of the filters were blasted in preparation for a new protective epoxy coating.

Both filters were charged with Leighton Buzzard sand and commissioned back into use.

The project was completed on time and in budget.